TEMAX / TIME III

Project Status: Execution

Map

Map: TEMAX-TIME III Projects
Enlarge

  • Location: Pennsylvania
  • Scope: (see detail below)
  • Capacity: 455 million cubic feet per day (mmcf/d)
  • Ownership: 100%
  • Project Completion Date: 2nd Half of 2010 and 2nd Half 2011
  • FERC Docket #CP09-68

Detailed Scope:

Compressor Station Facilities

  1. Install 13,333 horsepower (HP) Gas Unit and retire 1-2,000 HP Gas Unit
  2. Install 20,000 HP Electric Unit and upgrade 1-11,000 HP Electric Unit to 14,300 HP
  3. Install 27,000 HP Electric Unit, retire 3-2,500 HP Electric Units, and upgrade 1-11,000 HP Electric Unit to 14,300 HP
  4. Install 27,000 HP Electric Unit

Pipeline Facilities

  1. Install 0.5 miles of 36" diameter pipeline, pick up 9.2 miles of existing 20" and 24" diameter pipeline and relay 36" diameter pipeline
  2. Install 9.1 miles of 36" diameter pipeline loop
  3. Pick up 3.7 miles of existing 24" diameter pipeline and relay 36" diameter pipeline
  4. Pick up 6.8 miles of existing 24" diameter pipeline and relay 36" diameter pipeline
  5. Pick up 2.1 miles of existing 24" diameter pipeline and relay 36" diameter pipeline
  6. Pick up 2.4 miles of existing 24" diameter pipeline and relay 36" diameter pipeline
  7. Pick up 1.7 miles of existing 24" diameter pipeline and relay with 36" diameter pipeline, utilize existing 0.8 mile 36" diameter auxiliary river crossing, and install 26.5 miles of new 30" diameter pipeline

For more information, call 1.800.831.0043.